McKinley Field
Champaign, Illinois
McKinley Field
BOWA Construction provided CMAR services for Champaign Community Unit School District No. 4’s new 9,000 SF concession locker room building complete with a weight training room, film viewing area and locker rooms located at Central High School’s McKinley Field. Additional scope of work included demolition of the existing field house, dugouts and fence, and was replaced with a new running track; synthetic turf football field; long jump, pole vault, discus, and shot put areas; new football practice field; bleachers and press box; and a new parking lot.
Statistics
OWNER: CCUSD No. 4
COST: $6,604,515
PROJECT SCHEDULE: 05/2019 – 11/2019
SIZE: 9,000 SF